Mining Projects: Six Pitfalls that Threaten Delivery
Austmine Limited
/ Categories: Articles & Editorials

Mining Projects: Six Pitfalls that Threaten Delivery

Although it’s equally true of other industries, it seems that the mining industry doesn’t have a great record of on schedule and on-budget project delivery. Moreover, it also seems that it’s not very good at learning from experience either, and a cynical observer might be excused for thinking that the same old mistakes are being repeated time and again.

What are the factors that contribute to sub-optimal project delivery? These tend to include:

  • Poorly understood geological and geotechnical aspects of a deposit, leading to inappropriate mine and process flowsheet designs
  • Inadequate metallurgical test work
  • Funding availability during the investigation and engineering phases
  • Overly optimistic development schedules
  • Human factors, including over-optimistic expectations that are spurred on by the need to promote project attractiveness to prospective investors
  • Insufficient preparation for construction and operations during the Feasibility Study (FS) phase
  • Insufficient engagement with local communities, stakeholders, regulators, government agencies and NGOs

Find further analysis in Willis Towers Watson's report attached below. 

Image

Related Documents

Print
202
Previous Article Engineering Commissioning for Mining Projects
Return
Next Article The key? Collaboration — McLanahan talks its mining future

Austmine Programs

All Programs

Austmine Publications

All Publications

GET SOCIAL

SUBSCRIBE to our newsletter

Loading

Austmine

 

OZ METS Hub

WonderWebs.comTerms|Privacy|Copyright © 2018 Austmine | Mining Equipment, Technology and Services (METS) Sector
Back To Top